Thank you very much for your understanding; thank you for your willingness to help us explain to SET.
We are expected to finish the production of XDT-80 90000KGS in mid July. However, considering the following two points, it is suggested that ETA is scheduled in mid August.
1, Because the material is identified as the 9 type of dangerous goods, the Commodity Inspection Bureau will review relevant issues. We are worried that the CIQ will delay time.
2, The shipment may not be controlled, such as bad weather delays.
This is just about some uncontrollable factors, we will try to finish ETA ahead of time.